Edna May, WA
Forrestania Resources Limited (FRS) | PFS and Ore Reserve (4 releases) | Released 18 Sep 2026
Inferred share: Reserve-based, no Inferred
Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.
Planning inputs
Reserve-based, no Inferred | Overall slope about 38° (Stage 1), 26° (Stage 2) at Johnson Range, 26° to 38° at British Hill | Dilution 8% at Johnson Range, 9% others; mining recovery 90% at British Hill, 91% others
Also in the release
Mine life is project life; strip is waste:ore. Capex is project capital. Ore is processed at the Edna May plant. No NPV is given; cash flow is pre-tax and undiscounted at A$5,500/oz.
Read the release on the company's siteSee it in The Study Sheet, October 2026
Other pits in the same release
- FRSJohnson Range, WA | PFS | 18 Sep 2026
- FRSTycho, WA | PFS | 18 Sep 2026
- FRSBritish Hill, WA | PFS | 18 Sep 2026
Similar studies
- BCNLady Ida Project (Iguana Deposit), WA | PFS | 20 Aug 2026
- CMMMount Gibson Gold Project, WA | PFS | 27 Jul 2026
- MI6Bullabulling Gold Project, WA | PFS | 8 Jul 2026
- RRLMcPhillamys Gold Project, NSW | PFS | 19 Jun 2026
Browse the tracker
Published by Cognomine. Cognomine can solve a block model and return a practical plan in minutes.