Bullabulling Gold Project, WA
Minerals 260 Limited (MI6) | Pre-Feasibility Study and Maiden Ore Reserve | Released 8 Jul 2026
Inferred share: Inferred 3% of production target
Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.
Planning inputs
Inferred 3% of production target | Overall slope 31° oxide, 41° transitional, 51° fresh | Dilution 9%, ore loss 7% | Contract mining | Mining by Snowden Optiro and Orepath
Also in the release
LOM throughput grade 0.86 g/t Au at 90% recovery through a 5 Mtpa CIL plant. AISC A$2,520/oz, C1 A$2,130/oz. Separately, A$180M pre-FID capital and A$115M for pre-production operations.
Read the release on the company's siteAdded to the tracker; released before the first issue of The Study Sheet.
Similar studies
- CMMMount Gibson Gold Project, WA | PFS | 27 Jul 2026
- RRLMcPhillamys Gold Project, NSW | PFS | 19 Jun 2026
- BCNLady Ida Project (Iguana Deposit), WA | PFS | 20 Aug 2026
- FRSBritish Hill, WA | PFS | 18 Sep 2026
Browse the tracker
Published by Cognomine. Cognomine can solve a block model and return a practical plan in minutes.