Abercromby Gold Project, WA
WA Gold Limited (WAU) | Scoping Study (Stage 1 Mine) | Released 22 Apr 2026
Inferred share: Inferred ~10% of production target
Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.
Planning inputs
Inferred ~10% of production target | Overall wall angles 35° (open pit, first-pass optimisation) | Contractor mining | Mine plan by Intermine Engineering Consultants
Also in the release
Open pit (497kt at 1.64 g/t Au) then underground (1,160kt at 2.60 g/t Au), toll treated at 94% recovery. AISC A$4,204/oz open pit, A$2,938/oz underground. Table 1 NPV A$229m.
Read the release on the company's siteAdded to the tracker; released before the first issue of The Study Sheet.
Similar studies
- LGMMt Carrington Project, NSW | Scoping | 12 May 2026
- NMTIronclad, Barrambie Gold Project, WA | Scoping | 19 Mar 2026
- PRXHyperion Gold Deposit, Tanami North, NT | Scoping | 27 May 2026
- SHNLiontown Gold Operation, Qld | Scoping | 16 Feb 2026
Browse the tracker
Published by Cognomine. Cognomine can solve a block model and return a practical plan in minutes.