Van Uden Gold Project, WA

TG Metals Limited (TG6) | Scoping study (laterite heap leach) | Released 29 Sep 2026

Mine life
30 months
LOM; circa 3 years in the highlights
Strip ratio
0.6
Waste to ore, tonnes
NPV
~A$26.8 million
Pre-tax, 8%
Capex
A$14.2 million
Pre-production, incl. contingency

Inferred share: Inferred 15% of schedule

Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.

Planning inputs

Inferred 15% of schedule | Wall angle 60° in pit design; 40° overall assumed by On The Crest Mine Planning | Dilution 5%, mining recovery 95% | Four mining blocks

Also in the release

Free-dig laterite at 0.61 g/t Au feeds a 250,000 tpa heap leach at 90% gold recovery. AISC A$2,835/oz.

Read the release on the company's siteSee it in The Study Sheet, October 2026