Tuckanarra Gold Project, WA

Odyssey Gold Limited (ODY) | Stage 1 Scoping Study | Released 9 Jul 2026

Mine life
29 months
Initial mine production, Cable Pit
Strip ratio
11.9:1
LOM, waste to ore
NPV
Not disclosed
Not disclosed
Capex
~A$7 million
Pre-production

Inferred share: Inferred ~17% of target; 18% in risk section

Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.

Planning inputs

Inferred ~17% of target; 18% in risk section | Overall 36° oxide, 42° transitional, 47° fresh; batter 55°, 60°, 65° | Dilution 15%, mining recovery 95% | Contractor mining | Mine plan by GTS

Also in the release

1.35Mt at 1.9g/t Au hauled 195km for toll treatment at Kirkalocka, 95% recovery. Operating costs ~A$3,400/oz (pre-tax); net pre-tax cashflows ~A$180 million at A$6,000/oz.

Read the release on the company's siteAdded to the tracker; released before the first issue of The Study Sheet.