Lady Herial (Kambalda Gold & Nickel Project), WA

Lunnon Metals Limited (LM8) | Feasibility Study and initial Ore Reserve | Released 16 Jan 2026

Mine life
8-10 months
Mined and processed
Strip ratio
5.9:1
Detailed mine design
NPV
Not disclosed
Not considered a key measure
Capex
~$1.0-1.5 million
Nominal pre-development sum

Inferred share: Reserve-based, no Inferred

Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.

Planning inputs

Reserve-based, no Inferred | Inter-ramp 25° saprolite, 36° sector B, 33° sector C | Dilution 20%, ore loss 5% in optimisation; ~48% dilution in bench design | Contractor mining

Also in the release

Proved Ore Reserve 268,250t @ 1.89g/t Au, sold to SIGM for the Lefroy plant at 91.0% recovery. AIC $2,354/oz. Pre-tax free cash flow $40.4M (70% share) at $6,250/oz. Mine design by MGT.

Read the release on the company's siteAdded to the tracker; released before the first issue of The Study Sheet.