Port Gregory Garnet Project, WA
Heavy Minerals Limited (HVY) | Pre-Feasibility Study and maiden Ore Reserve | Released 29 Jul 2026
Inferred share: Inferred ~5.7% of mill feed
Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.
Planning inputs
Inferred ~5.7% of mill feed | Batter face angle 34°, inter-ramp angle 26.8° (multi bench) | Dilution and mining recovery not disclosed | Mining, geotechnical and Ore Reserve by AMC Consultants
Also in the release
Free-digging strandline sands, mined by scraper and surface miner, at 4.4% THM feed a 3.63 Mtpa plant; garnet recovery 87.0% in test work. Unit operating cost A$498.60/t product. IRR 47.6%.
Read the release on the company's siteAdded to the tracker; released before the first issue of The Study Sheet.
Similar studies
- CMMMount Gibson Gold Project, WA | PFS | 27 Jul 2026
- CMGLindfield Vanadium Project, Qld | PFS | 20 Jul 2026
- SKYTallebung Project, NSW | PFS | 10 Aug 2026
- VTMNorth Stanmore Heavy Rare Earth Project, WA | PFS | 18 Aug 2026
Browse the tracker
Published by Cognomine. Cognomine can solve a block model and return a practical plan in minutes.