Kookynie Gold Project, WA
Carnavale Resources Limited (CAV) | Open pit BFS and maiden Ore Reserve | Released 26 Oct 2026
Mine life
18 months
Open pit mine life
Strip ratio
Not disclosed
Ore 220kt, waste 9,851kt
NPV
A$87 million
Pre-tax, 8%, A$6,000/oz base case
Capex
A$24m
Max drawdown, KGP basis (Carnavale 80%)
Inferred share: Reserve-based, no Inferred
Figures are as the company states them, in its currency and on its basis. "Not disclosed" means the release doesn't state the figure.
Planning inputs
Reserve-based, no Inferred | Face angle 50° to 80° Swiftsure west, 50° to 65° east, 50° to 70° Tiptoe | Dilution 24%, mining recovery 100% | Contract mining | Mine plan by Cube Consulting
Also in the release
Ore 220kt at 5.0g/t for 35.6koz under an Ore Purchase Agreement. AISC A$2,721/oz. Pre-production capital for the open pit A$2.4m.
Read the release on the company's siteSee it in The Study Sheet, November 2026
Similar studies
- HRNGum Creek Gold Project, WA | DFS | 22 Jul 2026
- BTRGoldfields Project (Menzies and Laverton), WA | DFS | 29 Jan 2026
- LM8Lady Herial (Kambalda Gold & Nickel Project), WA | DFS | 16 Jan 2026
- TG6Van Uden Gold Project, WA | Scoping | 29 Sep 2026
Browse the tracker
Cognomine can solve a block model and return a practical plan in minutes.